Mid July 2022 Update

Surveyors plotting the center line of the new train tracks

Surveyors plotting the center line of the new train tracks

Welcome back for our mid July update, where we’ll catch you up on the goings on around the park.

Stakes mark the offset of the new train track center line

Stakes mark the offset of the new train track center line

First things first; Train construction update. Folks, it is about to get real here in the park. We now have multiple crews working in different areas doing different tasks. For example, today there is a survey crew working on staking out the center line of the rails so that the rail crew knows where to locate the new tracks correctly. Also, the electricians are hard at work running the new power to the charging stations used by the trains.

As the month progresses you’ll see even more workers do all kinds of work. Trees are being cut, rocks are being moved, platforms will be removed and many other tasks.